What Must Happen before a Construction Defect Lawsuit in Florida?
Before filing a construction defect action, Chapter 558, Florida Statutes, requires the claimant to serve a written notice of claim on the contractor, subcontractor, supplier or design professional. Section 558.004(1) requires service at least 60 days before filing, or at least 120 days for an association representing more than 20 parcels.
The notice must refer to Chapter 558 and describe each alleged defect in reasonable detail, along with any known damage. Based on at least a visual inspection, it must identify each defect's location well enough for the responding party to find it. Destructive testing is not required for the notice.
Within 30 days after service, or 50 days for an association of more than 20 parcels, the person served is entitled to a reasonable inspection of the property. Within 10 days after service, or 30 days for an association representing more than 20 parcels, that person may serve a copy of the notice on each contractor, subcontractor, supplier or design professional it reasonably believes is responsible for a defect in the notice.
Within 45 days after service, or 75 days for a large association, the person served must give a written response. The response may offer to repair, offer to pay, offer both, dispute the claim, or state that the insurer will decide on payment. The claimant then has 45 days to accept or reject a settlement offer in writing.
If the claim is disputed or no timely response arrives, the claimant may file suit without further notice. Under section 558.003, a suit filed without following the chapter is stayed on timely motion until the claimant complies. Serving the notice tolls the statute of limitations for the period set out in section 558.004(10) but does not toll a statute of repose.
The chapter applies to claims for damage to property, not personal injury claims. Under section 558.003, notice is not required for a project that has not reached the stage of completion of the building or improvement. Under section 558.005(1), the chapter applies to claims based on a construction defect that has arisen after completion of a building or improvement, when the agreement to make the improvement was made after October 1, 2009, unless a claimant and a potential defendant agreed in writing to opt out of the requirements of that section. Payment disputes can lead instead to a construction lien.
This post is for informational purposes only and does not constitute legal advice or create an attorney-client relationship. Always consult a licensed attorney in your jurisdiction for advice tailored to your circumstances.
News
- Indian Harbour Beach City Council Item 10.f: SOIRL 19-72 Muck Removal Funding Amendment on October 27
- Florida Condo Citation Rule 61B-21.0026 and Minor Violation Changes Take Effect November 12, 2026
- Titusville City Council Item 8.A: FY27 Road Resurfacing Program and Street List on October 27
- Titusville Resolution 25-2026: City Council Vote on U.S. Space Academy Location on October 27
- Titusville Affordable Housing Advisory Committee: 2027 Housing Incentive Plan Review on November 2
- Indian Harbour Beach Ordinance 2026-09: City Council Second Reading on Comprehensive Plan Update on October 27
- Titusville Board of Adjustment and Appeals Variance No. 23-2026: Starling Honda and GMC Dealership Signs on October 28
- Social Security 3.6% Cost of Living Increase Takes Effect December 2026
- Titusville Ordinance 43-2026: City Council Second Reading on Open Space Standards on October 27