How long does a contractor have to record a construction lien in Florida?
A Florida contractor must record a claim of lien no later than 90 days after last furnishing labor, services or materials, and the lien generally expires after 1 year.
Section 713.08, Florida Statutes, allows a claim of lien to be recorded at any time during the work, but no later than 90 days after the lienor's final furnishing of labor, services or materials. A separate 90 day deadline can apply when the original contract is terminated.
The claim must be served on the owner before recording or within 15 days after recording, or it may become voidable. Under section 713.22, the lien generally expires 1 year after recording unless an action to enforce it is filed.
This post is for informational purposes only and does not constitute legal advice or create an attorney-client relationship. A licensed attorney in the relevant jurisdiction should be consulted for advice tailored to specific circumstances.
News
- IRS Final Automatic Enrollment Rules Apply After December 31, 2027
- Palm Bay City Council Item 6: Former Majors Golf Course and Eden at Bayside Lakes Land Acquisition on November 19
- Florida Bid to Host U.S. Space Academy at Kennedy Space Center and UCF Announced on November 17
- Titusville Planning and Zoning Commission Item 9.A: Capital Improvements Element Update for 2027 to 2031 on November 18
- Florida Condo Meeting Rule 61B-23.001 Takes Effect November 30, 2026
- Sebastian City Council Ordinance O-26-33: Heavy Industrial Zoning District Lot Size and Setback Changes on November 18
- Palm Bay City Council Item 2: 911 Dispatch Move to Brevard County Sheriff Unified Communications Center on November 19
- Cocoa Beach City Commission Ordinance 1730: Master Capital Project and Service Special Assessments First Reading on November 19
- Melbourne Planning and Zoning Board Item 9: Digital Light Drive Warehouse Site Plan PLAN2026-0009 on November 19