How long does a contractor have to record a construction lien in Florida?
A Florida contractor must record a claim of lien no later than 90 days after last furnishing labor, services or materials, and the lien generally expires after 1 year.
Section 713.08, Florida Statutes, allows a claim of lien to be recorded at any time during the work, but no later than 90 days after the lienor's final furnishing of labor, services or materials. A separate 90 day deadline can apply when the original contract is terminated.
The claim must be served on the owner before recording or within 15 days after recording, or it may become voidable. Under section 713.22, the lien generally expires 1 year after recording unless an action to enforce it is filed.
News
- Brevard County Commission Item J.2: AMC Malabar Property Purchase Near Jordan Scrub Sanctuary, October 20
- Brevard County Commission Item J.1: Gamopin Land Purchase for West Cocoa Mud Lake Stormwater Project, October 20
- Brevard County Commission Ordinance Creating the Brevard Barrier Island Land Authority: Public Hearing October 20
- Florida Community Association Manager Citation Rule Takes Effect October 27, 2026
- IRS Trump Account Auto Enrollment Rules Became Effective September 30, 2026
- West Melbourne Ordinance 2026-09: City Council Second Reading on Residential Compatibility Rules, October 20
- IRS Proposes Farmland Sale Installment Tax Rules, Comments Due November 30, 2026
- Florida Condo Board Education Rule Became Effective September 3, 2026
- Florida Appraiser Continuing Education Rule Became Effective October 6, 2026